COMPANIES GUIDE
CATEGORIES
 
   

 
PROFESSIONALS
 
   
New task for Noble to tackle nonconformities on jack-up rig

Norwegian offshore safety regulator has carried out an audit of the management of materials handling and the
working environment on one of Noble's jack-up rigs, currently working for Aker BP off Norway, and is awaiting a
response from the offshore drilling contractor regarding the way the identified nonconformities will be handled.

The Petroleum Safety Authority Norway (PSA) recently revealed that it had conducted the audit from 17 to 23
February 2023 with the objective of verifying that Noble's management of materials handling and the working
environment on its Noble Integrator jack-up rig complied with the regulatory requirements.

While conducting its investigation, the offshore safety watchdog identified several breaches of the regulations.
The ten nonconformities that the regulator found concern procedures for lifting operations; operationally
responsible entity for the drill floor during day time; MOB boat forerunners; transfer of information when changing
shifts and crews; joint, local working environment committee (FS-AMU); the safety service; training related to
health risks; management of the psychosocial working environment; overview of working environment risks and
presentation of analyses; and non-conformity handling.

In addition, the regulator observed five factors it categorised as improvement points regarding daily checks of
offshore cranes, secondary evacuation route from offshore cranes, pre-use checks of lifting equipment,
competence management, and materials handling of steel plates.

In line with the findings of the PSA's audit, the offshore safety watchdog has asked Noble to report how these
nonconformities will be addressed and provide its assessment of the improvement points observed.

The 2014-built Noble Integrator is a Gusto MSC CJ70 X150 MD jack-up rig, which was constructed at Keppel
FELS shipyard in Singapore. It can accommodate 150 people. Capable of working in a water depth of 492 ft, the
rig's maximum drilling depth is 40,000 ft.

Previously, Aker BP contracted the rig under the frame agreement with Maersk Drilling in 2017 when the Aker BP
Jack-up Alliance, including Halliburton, was established. In December 2021, a deal to renew the frame
agreement was disclosed.

The Noble Integrator rig secured more work with Aker BP after the Norwegian player entered into drilling and
wells alliance agreements in January 2023 with Noble Corporation, Odfjell Drilling and Halliburton to carry out
drilling activities on the Norwegian continental shelf (NCS).

Noble seems to be reaping the benefits of its merger with Maersk Drilling, as its total backlog recently rose to
$4.6 billion, thanks to the new deals totalling $1.1 billion, secured during the first quarter of 2023.
Offshore Energy Today




 
FEATURES
 
 


 

 
ADVERTISING
 
 
 

 
PARTNERSHIP
 
 
 
 

 
  Copyright © 2009 - Guia Oil e Gas Brasil